SECI Awards 125MW/500MWh Odisha BESS Projects to Coal India and Onward Solar

0
352

Solar Energy Corporation of India (SECI) has concluded its auction for 125 MW/500 MWh of standalone Battery Energy Storage Systems (BESS) in Odisha, marking another step toward strengthening India’s clean energy and grid reliability framework.

The auction discovered tariffs ranging between ₹3.04 per kW per month and ₹3.75 per kW per month.

Coal India Limited emerged as a key winner, securing Cluster I comprising two 20 MW/80 MWh projects, totalling 40 MW/160 MWh, at a tariff of ₹3.04 per kW per month. The company also won Cluster II, which includes two additional 20 MW/80 MWh projects with a combined capacity of 40 MW/160 MWh, at ₹3.05 per kW per month.

Onward Solar Power secured the remaining 45 MW/180 MWh capacity at a tariff of ₹3.75 per kW per month.

The tender, issued in December 2025, is backed by Viability Gap Funding under the Power System Development Fund. The projects are intended to provide on-demand energy storage support to GRIDCO Limited.

See also  ACME Solar Holdings Limited Commissions Sixth Phase of BESS Project in Jaisalmer

The BESS installations will be deployed across six substations in Odisha — Padampur, New Bolangir, Bhatli, Basta, Narendrapur and Tentuli Khunti — with the objective of enhancing grid stability during peak and off-peak demand periods.